STS-107 · 16 January to 1 February 2003 · The sky over Texas
Sources: NASA, STS-107 mission page; CAIB report, Board Statement.
Sources: CAIB report Vol. I (2003): Board Statement and chapter 3 (81.7 s); section 6.1 (65/79 flights, design requirement); section 6.3 (three imagery requests); chapter 7, p. 191 (the slide, 640 times); chapter 8, p. 195.
Seventeen years after Challenger, the same organisation had a new safety office and a whole book of lessons. Why did it lose a shuttle to the same old mistake: a repeated defect treated as normal, and engineers once again asked to prove there was danger?
Source: CAIB report, section 6.1 (seven foam losses, how they were classified) and 6.3 (imagery requests, the 24 January conclusion).
Timeline from chapter 3 and section 6.3 of the CAIB report. Times are US Eastern.
Sources: CAIB report, chapter 3, pp. 49, 54, 60, 65 (launch time, 81.7 and 81.9 s, panel 8, 545 mph, re-entry times); section 6.3 (17 Jan log, Boeing's estimate, Rocha's e-mail, cancellation at 8:30, 23 Jan e-mail). Chapter 3 also gives a 625–840 ft/s range from image analysis.
"NASA's organizational culture and structure had as much to do with this accident as the External Tank foam."
Source: CAIB report, chapter 7, p. 177.
| Challenger 1986 | Columbia 2003 | |
|---|---|---|
| Repeated damage | O-ring distress on 7/23 flights | foam shedding on 65/79 imaged flights |
| Softer labels | "not desirable but acceptable" | "in-family", "accepted risk" |
| Burden of proof | prove it is NOT safe | prove unequivocally there is a problem |
| Schedule pressure | target of 24 flights a year | Node 2 on 19 February 2004 |
| Safety office | not invited to the call | lacked "the independence and authority" |
| Presentation | a chart without the zeros | a slide that buried the key line |
Sources: Challenger column: Rogers Commission report (1986), chapters 5–8, and Dalal, Fowlkes and Hoadley (1989); see piece #01. Columbia column: CAIB report, sections 6.1, 6.2, 6.3, chapter 7 (pp. 191, 192). The row-by-row pairing is Mark's; CAIB chapter 8 says the decisions on foam and on O-rings "had identical trajectories".
13 things often said about Columbia, checked against the original record. Tap a row for the reasoning.
The Board's finding on the physical cause (Board Statement, chapter 3), backed by launch film, sensor data inside the wing and the foam-impact test.
Foam shedding on 65 of 79 imaged flights; seven losses from the left bipod ramp; a design requirement banning debris (CAIB, section 6.1).
Three separate requests, none through the formal channel. The request to the military was cancelled on the morning of 22 Jan, 90 minutes after it was made (CAIB, section 6.3).
The Node 2 date of 19 Feb 2004 "influenced many of decisions", and during the flight managers worried about the strike's effect on the launch schedule (CAIB, section 6.2, F6.2-7).
Chapter 8: the causes of the institutional failure behind Challenger "have not been fixed"; dangerous aspects of NASA's 1986 culture "remained unchanged".
The study for the Board called the rescue "challenging but feasible", provided the damage was recognised before Flight Day 7. It was done after the accident, and rushing Atlantis to launch carried its own risk. "Possible" is right; "certain" is not.
The slide is the most memorable symptom. The Board gave it a sidebar in chapter 7, but concluded that culture and structure "had as much to do with this accident" as the foam. Remove the slide but keep the question "is there a requirement?" and the outcome might well have been the same.
A loss of about 40 percent in purchasing power is real context. But the Board says the roots "can also be traced, in part," to the post-Cold War policy environment, and does not call it a direct cause (CAIB, chapter 5, pp. 99, 104).
The hole was in the reinforced carbon-carbon (RCC) leading edge, panel 8, not in the tiles on the orbiter's belly. Both are part of the thermal protection system, so this is only half right (CAIB, chapter 3).
The crew survival report (NASA, 2008): about 40 seconds passed between loss of control and cabin depressurisation, and "part of this short timeframe was undoubtedly employed in recognizing that a problem existed". After depressurisation the crew were incapacitated "within seconds". The accident "was not survivable".
The most repeated line. The Board wrote that had managers understood the threat, repair and rescue plans "would most likely have been developed, and a rescue would have been conceivable" (CAIB, section 6.4). The truer line: you cannot save what you refuse to look at.
That was also many engineers' feeling in 2003: a 17 Jan e-mail said the debris "didn't look like a big enough piece to pose any serious threat". The 7 July 2003 test fired 1.67 lb of foam at panel 8 and made a hole about 16 inches across (CAIB, section 6.3; CAIB test photo).
Managers believed there was no dangerous damage, so the e-mail to the crew said "absolutely no concern for entry" (CAIB, section 6.3). In 2013 Wayne Hale recalled a colleague saying "if it has been damaged, it's probably better not to know", but said "There was never any debate about what to tell the crew" (AP, 2013, secondary). The real failure was refusing to look, not hiding.
Scores are Mark's assessment based on the sources in Part 8, not figures from a study.
Sources: CAIB report, chapter 7 (culture, independent technical authority) and chapter 8; CRS RS21606 (29 recommendations, 15 before return to flight); NASA, STS-114 page (26 July 2005, foam shed from the tank).
The disaster of an organisation that already had the answer in 1986, but kept it in a report instead of turning it into structure.
The Board made 29 recommendations, 15 of them required before flights resumed, including the ability to inspect and repair the thermal protection system in orbit and an independent technical authority. The return-to-flight mission, STS-114, launched on 26 July 2005. Launch imagery again showed a piece of foam coming off the External Tank, and an astronaut went outside to pull two protruding gap fillers from between the tiles.
This time, NASA looked. The Shuttle programme ended in 2011 after 135 flights and two losses: Challenger and Columbia.
Sources: CRS RS21606 (2003); NASA, STS-114 page; NASA (135 flights, 1981–2011).
For every risk report, every slide for the boss, every "known issue" on the backlog.
Sources: CAIB report, F6.1-10 (trend analysis), section 6.3 (Crater, Rocha's e-mail). The 1986 line: "little or no trend analysis", Rogers Commission report, chapter 7.